Record field progress

Step 1 — Create the day's log: Go to FieldNew log. Select the date, fill in weather, workforce, and activity description. Save.

Step 2 — Record line item progress: In the log → Progress section → Add progress → select the estimate line item → enter quantity executed today (in the line item's unit). The system accumulates total progress.

Step 3 — Attach photo evidence: In the log → DocumentsUpload document → select photos or files.

Step 4 — Log issues (if any): Click New issue to document problems, accidents, or relevant situations with severity and actions taken.

How progress feeds Cost Control

Field progress drives EVM:

  • Earned Value (EV) = Σ (% progress × line item budget)
  • SPI and CPI update with each progress entry

View the impact in Cost Control → EVM metrics.

Best practices

  • Record progress at the end of each work day, not days later.
  • Be precise with quantities — overestimated progress distorts EVM.
  • Attach photos as backup for what was reported.
  • Document delays and their cause in log observations.